The Documents that Anchor My Projects
The documents I rely on most are the ones that help me keep track of where a project stands, what needs my attention, and what may affect the work ahead.
Every project requires documentation, and most organizations have requirements around what needs to be maintained. Some have structured governance frameworks with predefined templates and strict reporting expectations, while others identify the information that needs to be documented but provide more flexibility on how it is to be tracked. Over the past fifteen-plus years leading health IT initiatives across different environments, I have worked with both models, and that variability has shaped how I approach documentation and coordination.
Budget tracking and status reporting are part of every project, but reporting accurately requires a good understanding of what is going on. Timelines shift, dependencies change, risks emerge, and activities across different teams can affect progress. Keeping track of those moving pieces helps me understand where the project stands, what needs attention, and what may affect upcoming work.
Over time, I have come to consistently rely on five documents to help me do that. When an organization has required templates or tools, I use them as required and consider whether they include the information I normally track. Depending on what is available, I may add detail, use parts of the template differently, or maintain a separate working version alongside the organizational one. The format and level of detail will vary depending on the project, but the information I track is fundamental to how I organize, coordinate, and manage the work.
Project Schedule and Gantt Chart
A well-defined project schedule shows how work unfolds across people, activities, and timing. The Gantt view I maintain connects ownership, duration, status, and milestones so dependencies and sequencing can be seen together.
I typically build my working schedule in Excel or Sheets because they allow rapid adjustment, flexible structuring, and the use of colour to make milestones and critical path activities easy to identify at a glance. Activities are organized at a level that reflects the work being done, including workgroup coordination and build phases, with status incorporated alongside timing.
Time is structured at the daily level so holidays, weekends, and resource availability can be factored into the schedule. This becomes particularly important when specialized technical or clinical resources are involved or when several activities are competing for time around key milestones.
The project schedule is one area where I often maintain my own working version, even when an organizational tool is already in use. Enterprise tools can contain extensive scheduling information, but I find my working version makes it easier to look at the day-to-day realities of the project with the team. Where I maintain both, I routinely reconcile them so the information remains consistent.
RAID Log
Health IT initiatives unfold within environments shaped by vendor timelines, infrastructure readiness, governance checkpoints, and shifting clinical priorities. A consolidated RAID log gives me a structured way to keep track of factors that may influence delivery as the project progresses. I use it to maintain visibility across four areas:
⚠️ Risks – Potential events that may affect progress, documented with the likelihood, impact, ownership, and mitigation considerations
💭 Assumptions – Conditions believed to be true that planning decisions rely on, recorded for validation and future review
🛠️ Issues – Active challenges requiring resolution, tracked with ownership, priority, and status
🔗 Dependencies – External activities or deliverables outside project control that influence sequencing and timing
Keeping these together gives me a consistent reference for what requires follow-up or may need to be raised through project or governance discussions. It also helps preserve context as circumstances change throughout the project.
Communication Plan
Communication planning in a health IT initiative is about more than distributing updates. Different groups need different information at different points in the project, and who delivers that information can matter as much as when and how it is communicated. For each project, I maintain a communication plan documenting:
👩🏻⚕️ Who needs information
❓ What they need to understand
🧭 When they need to know
📫 How messages will be delivered
🗣 Who is positioned to deliver them
This gives me a way to coordinate responsibility for drafting and delivery while keeping communication connected to project activity. It also helps me identify where communication may be missing or excessive and to adjust plans when timelines change without creating conflicting messages.
Test Plan
Most projects I lead involve clinical applications and EHR environments, where the objective is confirming that configuration changes, workflows adjustments, and integrations behave as intended within operational settings. I use the test plan to coordinate and track validation activities across teams. It identifies the scenarios and functional areas that need to be tested, while the detailed test scripts are maintained separately.
The document brings together the elements needed to organize testing efforts:
🧩 Testing scope – New functionality being validated, along with regression requirements to confirm adjacent areas continue to work as expected
📋 Testing scenarios – Scenarios that need to be completed and what each one is intended to test
👥 Ownership and participation – Responsibility for drafting each script, along with the analysts, subject matter experts, and end users needed to execute it
🗓️ Timing and sequencing – Planned testing windows and any sequencing requirements that help minimize duplication or make better use of resource time
Keeping this information together helps me see how the different testing activities fit together, track progress as testing moves forward, and identify where coordination may be needed.
Implementation Plan
The implementation plan focuses on the activities surrounding go live. This is often a concentrated period of work across technical, application, and operational teams where timing, sequencing, and ownership must be clear.
Every project I lead includes a detailed implementation plan that defines the activities to be completed during this period. This include step-by-step configuration activities, communication handoffs, sequencing considerations, and timing estimates. It also captures validation steps, decision points, and contingencies that may be activated if conditions change during execution.
This gives everyone involved in the transition a common reference for what needs to happen, in what order, and who is responsible. Clinical and administrative areas can plan resources around expected timing, while the project team can respond when activities take longer than expected or someone becomes unavailable without losing sight of what still needs to happen.
Keeping Project Information Connected
What has kept these five documents part of my approach is how they work together. A change to the schedule may affect a dependency, alter when communication needs to occur, shift testing, or change implementation timing. Keeping each document current helps me carry those changes through the project rather than looking at each area independently.